Review the project specifications developed by the Interior Designer
Review the Operator’s FF&E and OS&E Brand Standards
Derived from the BOQ and the specifications, estimate the project budget for the FF&E and OS&E packages
Shortlist and pre-qualify most suitable manufacturers for this market segment
Manage the bidding process with the pre-selected bidders
Prepare comparison charts and awarding recommendation
Manage the process of establishing all Purchase Orders and Contracts, and subsequent administration
LOGISTICS
Manage the manufacturing process, from the preparation and approval of shop drawings through to approval of samples, follow up of the manufacturing schedule, etc.
Develop a logistics strategy for the shipping, storage and delivery to the site of all goods
Manage the transportation of all goods from Ex-works delivery to on site delivery
INSTALATION
Develop an installation program by phases, compatible with the overall project schedule
Shortlist, bidding, awarding recommendation and contract negotiation of the installation of the FF&E and OS&E packages for the project
Manage, under a fast track formula the bidding, acquisition, manufacturing and installation for the mock up unit of the project
Develop and keep up to date all the control logs required for an effective management of the process
Create and manage a cost management system for the FF&E and OS&E packages, including the development of a monthly report to the Client
Manage the final acceptance process for the FF&E and OS&E packages for the project
Wrap up the cost; gather warranties, fire certificates, cleaning instructions, etc., of all elements installed